1. Develop the precedence diagram network(activity on node) (10 points) for the following project and then calculate the EST, EFT, LST, LFT, total float, minimum total duration and find out critical path(s) (20 points).
Activity
Duration(days)
must follow operations
A
10
-
B
15
-
C
8
A, B
D
12
A
E
2
B, C
F
5
C
G
6
C
H
8
D, E, F, G
◎ the precedence diagram network(activity on node) (10 points) for the following project
◎ the EST, EFT, LST, LFT, total float, minimum total duration and find out critical path(s)
Activity
Duration
(days)
EST
EFT
LST
LFT
TF
CP
A
10
0
10
5
15
5
B
15
0
15
0
15
0
○
C
8
15
23
15
23
0
○
D
12
10
22
17
29
7
E
2
23
25
27
29
4
F
5
23
28
24
29
1
G
6
29
29
23
29
0
○
H
8
29
37
29
37
0
○
Minimum total duration : 37 days
CP = START → B → C → G → H → END
total : 37days
2. Develop the `activity on arrow diagram` network for the following precedence diag…(To be continued )
[공부자료] CM의 공정표 , [공부자료] CM의 공정표기타시험족보 , 공부자료 CM 공정표
공부자료,CM,공정표,기타,시험족보
![[공부자료]%20CM의%20공정표_hwp_01.gif](http://www.allreport.co.kr/View/%5B%EA%B3%B5%EB%B6%80%EC%9E%90%EB%A3%8C%5D%20CM%EC%9D%98%20%EA%B3%B5%EC%A0%95%ED%91%9C_hwp_01.gif)
![[공부자료]%20CM의%20공정표_hwp_02.gif](http://www.allreport.co.kr/View/%5B%EA%B3%B5%EB%B6%80%EC%9E%90%EB%A3%8C%5D%20CM%EC%9D%98%20%EA%B3%B5%EC%A0%95%ED%91%9C_hwp_02.gif)
![[공부자료]%20CM의%20공정표_hwp_03.gif](http://www.allreport.co.kr/View/%5B%EA%B3%B5%EB%B6%80%EC%9E%90%EB%A3%8C%5D%20CM%EC%9D%98%20%EA%B3%B5%EC%A0%95%ED%91%9C_hwp_03.gif)
![[공부자료]%20CM의%20공정표_hwp_04.gif](http://www.allreport.co.kr/View/%5B%EA%B3%B5%EB%B6%80%EC%9E%90%EB%A3%8C%5D%20CM%EC%9D%98%20%EA%B3%B5%EC%A0%95%ED%91%9C_hwp_04.gif)
![[공부자료]%20CM의%20공정표_hwp_05.gif](http://www.allreport.co.kr/View/%5B%EA%B3%B5%EB%B6%80%EC%9E%90%EB%A3%8C%5D%20CM%EC%9D%98%20%EA%B3%B5%EC%A0%95%ED%91%9C_hwp_05.gif)
순서
[공부자료(data)] CM의 공정표
설명
다.